COMING FULL CIRCLE

team collaboration was the key to success for eCho.

from day one to move-in, it set the tone for building a

reliable, redundant, scalable and flexible mission

critical facility that met all the owner’s objectives and

brought the team’s Guiding principles to life.

“the syska hennessy/Corgan team, combined with

turner Construction, translated some basic

requirements into a state-of-the-art facility on a modest

budget. by asking questions, listening carefully and

then coming back with options and recommendations

at every step of the process, the design and

construction teams assimilated our underlying mantra

of reliability, availability and maintainability for this data

center. they were the consummate collaborative

partners,” said bill badger, project Manager, Cps

energy. “we would sketch out ideas on a dry erase

board or over a web conference. in short order, those

ideas were integrated into the design and construction

of the building. for Cps energy, this was the perfect

integration of owner, designer and builder. eCho is

the tangible result of the best teamwork on the

planet.”

VITAL STATS:

the Cps energy’s Mission Critical Control and data

Center (eCho) was built with concurrently

maintainable goals in mind, with a feed from two utility

sub stations, allowing for a robust system while

maintaining the overall budget constraint. supporting

multiple operating groups under a single roof, the

facility is awaiting leed Gold certification. eCho

features a control center operating space of 10,000 to

15,000 sq. ft. the facility’s data processing or white

space area is currently comprised of another 10,000

sq. ft. of space, with design provisions to double the

space and critical it load for future expansion.

7X24 MAGAZINE FALL 2015

Will Hodges, P.E. is Senior Associate at Syska Hennessy Group. He can be reached at 972-638-5406

Val Loh is Principal at Syska Hennessy Group. He can be reached at 212-556-3404

Bob Stickney is Principal at Syska Hennessy Group. He can be reached at 972-638-5420

cPs energy Mission critical

control and Data center

san antonio, texas

75,000 sq. ft.

opened 2015

Bill Badger, CPS Energy Project Manager

Refrigerant-based laminar cooling system located on the back

panel of each rack.